January 19, 2010
|
This week we received some aerial photos of the commercial site at Newbury. The photos were taken on December 12 and although some more recent construction is not included, these photos will provide you with the best views of the retail site as a whole.
Please use this site plan and labeled photo to better acquaint [...]
January 18, 2010
|
Throughout the recent turn in the weather, the crew at Newbury has continued to press on and has even started a new project at the site. The new project featured in this update is the construction of yet another surcharge, which will be the future site of a hotel. In addition to this new focus, [...]
January 6, 2010
|
Newbury is pleased to unveil the first phase of home sites that will be made available this Spring. As reported previously, we will begin model home construction in the next 30-45 days, weather permitting. This first neighborhood is comprised of 55 lots. Each home site has been designed to accommodate a [...]
December 30, 2009
|
This update will focus primarily on the work for the retail portion of the site. A great deal of earthwork has been completed over the past few months and the upcoming photos will show this substantial progress.
Below is site map to show where the photos were taken. The locations are numbered and have arrows indicating the [...]
December 28, 2009
|
This update will feature two key points of focus, those being the increasing retail site surcharge and the installation of road underdrains. We’ll also provide a few new shots of the upper portion of the residential site and detail its progress as it closes in on final grade.
Below are the site maps that show where [...]
December 15, 2009
|
This construction update will focus on the work of the sanitary sewer and storm drainage crews as they continue to quickly progress up the site drive and through the residential portion of the site. Finally, we’ll feature a few shots of the completed earthwork at the portion of the project that is closest to beginning [...]
December 3, 2009
|
In this update, we will track the progress of the Sanitary Sewer crew, as they have almost reached the top of residential hill. Also, we will show the progress of the earthwork operation on the residential site as well as the building pads and surcharge at the retail section of the site.
Below are the usual [...]
November 20, 2009
|
Here we are with another construction update. This one will focus on building pads at the retail site to utility work up the residential site drive to some of the same ongoing earthwork on the residential site from the previous construction update!
So we will be showing progress all the way up the hill.
These below are [...]
November 16, 2009
|
Our Fall Festival at the site was on a beautiful Sunday afternoon. It was an open event for the public to get and a first look at the site and where the homes are to be built!
Two dump trucks, an excavator, a roller and a D6 bulldozer were part of the main attraction where kids [...]
November 13, 2009
|
With our site contractor working double shifts (6am to midnight) Monday through Saturday, we continue to make excellent progress at Newbury. The ongoing earthwork operations are happening on the top of the residential hill area and the 84 Lumber site. There is also continued progress on the sanitary sewer line along the residential site drive!
Here [...]